Vehicle restraint barrier installed along length of maintenance access track adjacent to sheet piled flood defence wall - April 2023
Vehicle restraint barrier installed along length of maintenance access track adjacent to sheet piled flood defence wall - April 2023
Access steps - October 2022
Kerbs placed on access track - January 2023
Handrail placed on access steps - Jan 2023
Holesmouth Outfall improved maintenance access - April 2023
Avonmouth Docks Kings Weston Maintenance Access
Clearing existing material - Oct 2022
Placing Rock Armour - Oct 2022
Stair Plinths
Place concrete to access ramp
High Tide - Feb 2023
Precast Stairs installed - March 2023
Handrail installation - April 2023
Kings Weston Outfall improved maintenance access - April 2023
Access track and flood defence wall - October 2023
Access Gates - October 2023
Avonmouth Docks River Avon Sheet Piled Flood Defence Wall
Unexploded ordnance proving trench ahead of piling works - March 2022
Coring to remove obstructions ahead of piling - May 2022
Sheet piling along the River Avon - May 2022
Sheet piled flood defence wall installation - August 2022
Maintenance Access Path - March 2023
April 2023
Avonmouth Docks River Avon Precast Concrete Flood Defence Wall - handrail installation July
Avonmouth Docks River Avon Sheet Piled Flood Defence Wall - Legato Block tie in towards dock gates - July 2023
Sheet pile to precast wall transition - June 2023
Access stairs - August 2023
Sheet pile to precast wall transition - June 2023
Avonmouth Docks River Avon Precast Concrete Flood Defence Wall
Temporary flood defence constructed - July 2022
Concrete blinding placed as working surface for placing of precast concrete panels
Precast flood defence wall installation along River Avon - September 2022
Sandbag Headwalls - May 2023
Topsoil Reinstatement - February 2023
April 2023
Handrail installation July 2023
Avon Riverside Industrial Estate
Existing flood embankment along River Avon - January 2022
Improvements to flood embankment - February 2022
Improved flood embankment with maintenance access path - February 2022
Lamplighter's Marsh
Vegetation clearence - December 2019
Trial holes to locate existing services - October 2021
Installation of filter drain - March 2022
Placing of fill material to the earth embankment - August 2022
Precast concrete flood defence wall installation - October 2022
Precast concrete flood defence wall units - February 2023
Precast concrete slabs placed to protect fuel pipelines - February 2023
Flood gate - April 2023
Maintenance Access Track and Palisade Fence - April 2023
Footpath reinstatement - May 2023
Vehicle barriers - August 2023
Flood embankment topsoil preperation - September 2023
We use cookies to ensure that we give you the best experience on our website. If you continue to use this site we will assume that you are happy with it.OkPrivacy policy